4 On 3 Off, 3 On 4 Off: The 14-Day 4-3-3-4 Rota

Work four shifts, rest three, work three, rest four. The 4-3-3-4 rota repeats every 14 days, so your days off fall on the same weekdays every fortnight. For 24/7 cover with 12-hour shifts, each team is paired with a partner that works the days it has off.

Last updated 22 October 2026 · By the ShiftShow team

Plan this pattern in ShiftShowAll shift patterns

What is the 4-3-3-4 shift pattern?

The 4-3-3-4 shift pattern, also written 4 on 3 off, 3 on 4 off, is a 14-day cycle: four shifts on, three days off, three shifts on, four days off. Each team works seven shifts per fortnight. For 24/7 cover with 12-hour shifts, four teams are used, two on days and two on nights. Within each pair the partner team works exactly the days the first team has off, which gives it the sequence three on, three off, four on, four off (3-3-4-4).

The partner’s 3-3-4-4 is the 4-3-3-4 sequence in reverse order, not the same sequence started on a different day. “4 on 3 off” is also used for a 7-day pattern of four shifts and three days off every week; this guide covers the 14-day 4-3-3-4.

14 dayscycle length, then it repeats
7 shiftsand 7 days off in each cycle
4teams for 24/7 cover: 2 on days, 2 on nights
84 hoursevery 14 days with 12-hour shifts
4 in a rowlongest run of shifts
4 dayslongest break
≈183 daysa year with no shift starting, on average
All or noneweekends free for the two teams on each shift, with a Monday start

The two templates, in order

4 shifts on3 days off3 shifts on4 days off
3 shifts on3 days off4 shifts on4 days off

The fortnight, day by day

With day 1 on a Monday, the two day teams work like this:

4-3-3-4 and its partner with day 1 on a Monday
MonTueWedThuFriSatSun
Team A, week 1WorkWorkWorkWorkOffOffOff
Team A, week 2WorkWorkWorkOffOffOffOff
Team B, week 1OffOffOffOffWorkWorkWork
Team B, week 2OffOffOffWorkWorkWorkWork

Team A works Monday to Thursday in week 1 and Monday to Wednesday in week 2, and never works a Saturday or Sunday. Team B works Friday to Sunday in week 1 and Thursday to Sunday in week 2, so it works every weekend. Every date has exactly one of the two teams on duty.

Team A calendar (days)

Day shiftNight shiftOff (no shift starts)
Day 1Day shift
Day 2Day shift
Day 3Day shift
Day 4Day shift
Day 5Off
Day 6Off
Day 7Off
Day 8Day shift
Day 9Day shift
Day 10Day shift
Day 11Off
Day 12Off
Day 13Off
Day 14Off

Team B calendar (days)

Day shiftNight shiftOff (no shift starts)
Day 1Off
Day 2Off
Day 3Off
Day 4Off
Day 5Day shift
Day 6Day shift
Day 7Day shift
Day 8Off
Day 9Off
Day 10Off
Day 11Day shift
Day 12Day shift
Day 13Day shift
Day 14Day shift

How four teams cover 24/7

4-3-3-4: two day teams and two night teams across one 14-day cycle (day 1 = Monday)

Day1234567891011121314
MoTuWeThFrSaSuMoTuWeThFrSaSu
Team A (days)DDDD···DDD····
Team B (days)····DDD···DDDD
Team C (nights)NNNN···NNN····
Team D (nights)····NNN···NNNN
Day cover✓✓✓✓✓✓✓✓✓✓✓✓✓✓
Night cover✓✓✓✓✓✓✓✓✓✓✓✓✓✓

Swipe the table sideways to see every day of the cycle.

D = day shift, N = night shift, · = off. The bottom two rows check every date: ✓ means exactly one team is on that shift.

Teams A and C work the 4-3-3-4 template on the same dates; teams B and D work 3-3-4-4. Cover is exact: 28 shifts per fortnight from four teams working seven each, so the rotation has no spare team. Unless teams carry more people than each shift needs, any absence that needs covering means overtime or relief staff.

Hours and time off

Seven 12-hour shifts per 14 days is 84 hours a fortnight. With a Monday start team A works four shifts (48 hours) in week 1 and three (36 hours) in week 2, and team B works three, then four. Averaged over the fortnight that is 42 hours a week. Over a year it averages about 183 shifts and about 183 days with no shift starting. For night teams all of those shifts are nights.

No run of work is longer than four shifts and no break is longer than four days. Because 14 days is exactly two weeks, the same weekdays come round every fortnight for as long as the rota runs.

Weekends: which team gets them

On 4-3-3-4 the weekends are not shared equally between partner teams. Which team gets them depends on the weekday the cycle starts:

Fully free weekends a year by the weekday team A’s day 1 falls on
Team A’s day 1 is a…Team A (days)Team B (days)Team C (nights)Team D (nights)
MondayEvery weekend0Every weekend0
TuesdayEvery weekend0260
Wednesday26000
Thursday026026
Friday0Every weekend0Every weekend
Saturday0Every weekend00
Sunday0000

“Every weekend” means all 52 or 53 weekends in the year; 26 means every other weekend. A weekend counts as free only if you are not at work at any point on the Saturday or Sunday, so a night shift starting on Friday evening rules it out.

With day 1 on a Monday, teams A and C have every weekend free and teams B and D work every weekend. With a Sunday start no team has a fully free weekend.

4-3-3-4 compared with other 14-day rotas

Four-team 12-hour rotas on a 14-day work and rest cycle
PatternSequenceMost shifts in a rowLongest breakFree weekends (Monday start)
4-3-3-44 on, 3 off, 3 on, 4 off (partner 3-3-4-4)44 daysEvery weekend for one team on each shift, none for its partner
Pitman2 on, 2 off, 3 on, 2 off, 2 on, 3 off33 days26 for every team
PanamaSame as Pitman, rotating between days and nights33 days26 for every team
5-5-2-25 on, 5 off, 2 on, 2 off (partner 5-2-2-5)55 daysEvery weekend for the 5-5-2-2 day team, none for the other three teams

All four work seven shifts in every 14 days with 12-hour shifts, so the hours are the same. They differ in run length, break length and how weekends are split between teams.

ShiftShow app showing a colour-coded monthly shift calendar

Set up 4-3-3-4 in ShiftShow

  1. Open Smart Shift Builder and choose the date of your first shift.
  2. On the 4-3-3-4 team, add four blocks: 4 shifts, 3 off, 3 shifts, 4 off. On the partner team, add 3 shifts, 3 off, 4 shifts, 4 off, starting on day 5 of the other team’s cycle.
  3. Use day shifts for a day team or night shifts for a night team and set your shift times.

ShiftShow then shows your shifts up to 20 years ahead, and the alarm adjusts to each shift.

Get ShiftShow for Android

4-3-3-4 FAQ

What is a 4-3-3-4 shift pattern?

Four shifts on, three days off, three shifts on and four days off, repeating every 14 days. Each team works seven shifts per fortnight.

Is 4 on 3 off the same as 4-3-3-4?

Not always. “4 on 3 off” is also used for a 7-day pattern of four shifts and three days off every week. 4-3-3-4 adds a second week of three shifts and four days off, so the cycle is 14 days.

How many teams does 4-3-3-4 need for 24/7 cover?

Four with 12-hour shifts: two on days and two on nights. In each pair one team works 4-3-3-4 and its partner works the days in between, which is three on, three off, four on, four off (3-3-4-4).

How many hours a week is 4-3-3-4?

Seven 12-hour shifts, 84 hours, per fortnight. With a Monday start that is 48 hours in one week and 36 in the other. Averaged over the fortnight it is 42 hours a week.

Do you get weekends off on 4-3-3-4?

It depends on the start day and on which team you are in. With day 1 on a Monday, the 4-3-3-4 team on each shift has every weekend free and its 3-3-4-4 partner works every weekend.

Do days off fall on the same weekdays every time?

Yes. The cycle is exactly two weeks, so your days off fall on the same weekdays every fortnight.

Explore other shift patterns

The staff scheduling calculator works out the teams and staff for any number of days on and days off.